The delays come as households face rising energy bills, with Ofgem due to confirm the January price cap on 25 November and Cornwall Insight forecasting a 26% increase for a typical household.
Ofgem announced on 19 November that it will investigate why many protected and Phase 1 projects have received later connection dates than they held before reform. These are the projects given priority for the earliest connections under the new process. The regulator acknowledged that several projects in the queue are now delayed compared with their previous positions, in some cases significantly, even though a large amount of speculative capacity has been removed.
Enviromena said the inquiry deals with only part of the problem. Reform was meant to re-order the queue to prioritise ready to build projects but this exercise did not take place. UK Power Networks and National Grid Electricity Distribution have both said publicly that none of the projects in their regions that asked to be moved forward were advanced.
The company has raised further concerns with NESO and Ofgem over the past year. Network operators expected engineering studies from NESO in September that would enable them to finalise acceleration options for delayed connections, and those studies are still outstanding. NESO has also paused new Transmission Impact Assessments since summer 2025 further slowing the deployment of critical renewable energy infrastructure.
Enviromena has more than 300MW of solar and battery storage projects with planning consent, funding secured and supply chains ready. A further 300MW is expected to receive consent in the coming months.
Chris Marsh, CEO at Enviromena, said:
“It is good to see Ofgem looking critically at connections reform, and its focus on transparency, compensation and accountability is the right one. But the problems go well beyond delays associated with Phase 1 projects. Projects that met every test reform set, with consent, funding and supply chains in place, were never given the chance to connect early, and the studies that could bring dates forward are months late.
“A wider inquiry would show the full picture. Every month consented projects wait is a month of new low-cost power kept off the grid while bills are rising.”
Enviromena is calling on Ofgem to extend its inquiry to the whole connections reform process. That would cover how projects were chosen for priority, the outstanding NESO studies and the pause on new assessments.